Project Start Date: Mon 11/06/00
Project Finish Date: Thu 12/15/05
| ID | Percent_Complete | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
|---|---|---|---|---|---|---|---|
| 1 | 48% | BUSINESS CONTINUITY | 287.11 days | Thu 07/01/04 | Mon 08/08/05 | ||
| 2 | 50% | Office Management | 261 days | Thu 07/01/04 | Thu 06/30/05 | Belchior Mira | |
| 3 | 50% | Performance Management | 261 days | Thu 07/01/04 | Thu 06/30/05 | Belchior Mira | |
| 4 | 50% | HR Management System | 261 days | Thu 07/01/04 | Thu 06/30/05 | Belchior Mira | |
| 5 | 50% | Agency Network | 261 days | Thu 07/01/04 | Thu 06/30/05 | Belchior Mira | |
| 6 | 50% | Supervision of Staff | 261 days | Thu 07/01/04 | Thu 06/30/05 | Belchior Mira | |
| 7 | 50% | IT Policies and Procedures | 261 days | Thu 07/01/04 | Thu 06/30/05 | Belchior Mira | |
| 8 | 0% | Disaster Recovery | 65 days | Mon 01/10/05 | Thu 04/07/05 | ||
| 1 | 0% | Disaster Recovery Hot Site VITA - 2005 | 65 days | Mon 01/10/05 | Thu 04/07/05 | Norm Christensen | |
| 2 | 1% | Initial Planning Meeting | 1 day | Mon 01/10/05 | Mon 01/10/05 | Allen Kass[5%],Norm Christensen[5%] | |
| 3 | 0% | Spreadsheets to DIT | 1 day | Mon 01/31/05 | Mon 01/31/05 | Norm Christensen | |
| 4 | 0% | Telecommunications Requirements | 1 day | Mon 01/31/05 | Mon 01/31/05 | Allen Kass | |
| 5 | 0% | Intra-Agency Coordination/Planning | 3 days | Tue 02/01/05 | Thu 02/03/05 | Norm Christensen | |
| 6 | 0% | Test Requirements/Test Plan | 2 days | Mon 03/28/05 | Tue 03/29/05 | Norm Christensen | |
| 7 | 0% | Conduct Test | 1 day | Sat 04/02/05 | Sat 04/02/05 | 6 | Norm Christensen,Steve Hastey[25%],Allen Kass[25%] |
| 8 | 0% | Post-Test Meeting | 1 day | Mon 04/04/05 | Mon 04/04/05 | 7 | Norm Christensen,Allen Kass |
| 9 | 0% | Follow-up Report | 3 days | Tue 04/05/05 | Thu 04/07/05 | 8 | Norm Christensen |
| 9 | 49% | Quality Assurance and Configuration Manager | 287.11 days | Thu 07/01/04 | Mon 08/08/05 | ||
| 1 | 50% | CM | 287.11 days | Thu 07/01/04 | Mon 08/08/05 | ||
| 2 | 50% | CM Repository Update (On-going) | 261 days | Thu 07/01/04 | Thu 06/30/05 | Belchior Mira | |
| 3 | 50% | MS Projects Update (On-going) | 261 days | Thu 07/01/04 | Mon 08/08/05 | Belchior Mira | |
| 4 | 50% | Project Tracking - SCR's and PR's (On-going) | 261 days | Thu 07/01/04 | Mon 08/08/05 | Belchior Mira | |
| 5 | 8% | Projects Documentation (User's Guides) | 5 days | Thu 07/01/04 | Wed 07/07/04 | ||
| 6 | 50% | EEO Calculator | 3 days | Thu 07/01/04 | Mon 07/05/04 | Nancy Balderson | |
| 7 | 50% | Develop On-Line User's Guide | 3 days | Thu 07/01/04 | Mon 07/05/04 | Angela Barnes-Hargress | |
| 8 | 0% | e480 Query Tool | 5 days | Thu 07/01/04 | Wed 07/07/04 | Nancy Balderson | |
| 9 | 0% | Develop On-Line User's Guide | 5 days | Thu 07/01/04 | Wed 07/07/04 | AHRS | |
| 10 | 0% | eTrans Query Tool | 5 days | Thu 07/01/04 | Wed 07/07/04 | Nancy Balderson | |
| 11 | 0% | Develop On-Line User's Guide | 5 days | Thu 07/01/04 | Wed 07/07/04 | AHRS | |
| 12 | 0% | Writen Notices | 5 days | Thu 07/01/04 | Wed 07/07/04 | Nancy Balderson | |
| 13 | 0% | Develop On-Line User's Guide | 5 days | Thu 07/01/04 | Wed 07/07/04 | AHRS | |
| 10 | 24% | CLIENT-SERVER PROJECTS | 1211 days | Thu 04/26/01 | Thu 12/15/05 | ||
| 1 | 8% | SAS PROJECTS | 1063 days | Thu 04/26/01 | Mon 05/23/05 | ||
| 1 | 16% | Work Force Planning Projects | 905 days | Thu 04/26/01 | Wed 10/13/04 | ||
| 2 | 76% | PMIS / Non-PMIS 480 Data Corrections (ON HOLD) | 473 days | Mon 09/03/01 | Wed 06/25/03 | Nancy Balderson | |
| 3 | 100% | Perform Data Analysis | 10 days | Mon 09/03/01 | Fri 09/14/01 | Nancy Balderson,Keith Andersen | |
| 4 | 100% | Merge PMIS / non-PMIS Data Files from June 30, 2001 Forward | 30 days | Mon 09/24/01 | Fri 11/02/01 | 3 | Keith Andersen |
| 5 | 100% | Develop Recommendation for Data Integrity & Present to Management | 2 days | Mon 03/04/02 | Tue 03/05/02 | Nancy Balderson | |
| 6 | 0% | Remove Unacceptable Non-PMIS data from Query Database (On Hold) | 3 days | Mon 06/09/03 | Wed 06/11/03 | Keith Andersen | |
| 7 | 0% | Obtain Approval for Reload | 5 days | Thu 06/12/03 | Wed 06/18/03 | 6 | Nancy Balderson |
| 8 | 0% | Reload Database Upon Approval | 5 days | Thu 06/19/03 | Wed 06/25/03 | 7 | Keith Andersen |
| 9 | 13% | Security Profile Updates - Parent Agency + Sub-Agency Record Selection | 80 days | Mon 05/10/04 | Fri 08/27/04 | Balderson | |
| 10 | 100% | Perform Analysis | 5 days | Mon 05/10/04 | Fri 05/14/04 | ||
| 11 | 100% | Develop Specs | 5 days | Mon 05/17/04 | Fri 05/21/04 | 10 | |
| 12 | 0% | Update Security Profiles | 70 days | Mon 05/24/04 | Fri 08/27/04 | 11 | |
| 13 | 0% | eTrans Enhancements | 13 days | Thu 04/26/01 | Mon 05/14/01 | Balderson | |
| 14 | 0% | Split VDOT eTrans Data By Districts | 13 days | Thu 04/26/01 | Mon 05/14/01 | ||
| 15 | 0% | Analsyis & Design | 13 days | Thu 04/26/01 | Mon 05/14/01 | ||
| 16 | 0% | Development | 13 days | Thu 04/26/01 | Mon 05/14/01 | ||
| 17 | 0% | Implementation | 3 days | Thu 04/26/01 | Mon 04/30/01 | ||
| 18 | 0% | Add Data Field Definitions | 12 days | Thu 04/26/01 | Fri 05/11/01 | ||
| 19 | 0% | Analsyis & Design | 11 days | Thu 04/26/01 | Thu 05/10/01 | ||
| 20 | 0% | Development | 12 days | Thu 04/26/01 | Fri 05/11/01 | ||
| 21 | 0% | Implementation | 3 days | Thu 04/26/01 | Mon 04/30/01 | ||
| 22 | 3% | Implement OLAP Analysis and Reporting | 113 days | Mon 05/10/04 | Wed 10/13/04 | Keith Andersen | |
| 23 | 100% | Requirements Definition | 3 days | Mon 05/10/04 | Wed 05/12/04 | ||
| 24 | 100% | Define and Document Requirements | 2 days | Mon 05/10/04 | Tue 05/11/04 | ||
| 25 | 100% | Obtain Approval - AHRS | 1 day | Wed 05/12/04 | Wed 05/12/04 | ||
| 26 | 0% | Analsyis & Design | 50 days | Thu 07/01/04 | Wed 09/08/04 | 23 | |
| 27 | 0% | Training | 50 days | Thu 07/01/04 | Wed 09/08/04 | ||
| 28 | 0% | Develop Specs | 10 days | Thu 07/01/04 | Wed 07/14/04 | ||
| 29 | 0% | Obtain Approval - AHRS | 2 days | Thu 07/01/04 | Fri 07/02/04 | ||
| 30 | 0% | Development | 20 days | Thu 09/09/04 | Wed 10/06/04 | 26 | |
| 31 | 0% | Prepare Test Data | 5 days | Thu 09/09/04 | Wed 09/15/04 | ||
| 32 | 0% | Install in Test Environment | 20 days | Thu 09/09/04 | Wed 10/06/04 | ||
| 33 | 0% | Test | 7 days | Thu 09/09/04 | Fri 09/17/04 | ||
| 34 | 0% | Obtain Approval - AHRS | 3 days | Thu 09/09/04 | Mon 09/13/04 | ||
| 35 | 0% | Implementation | 5 days | Thu 10/07/04 | Wed 10/13/04 | 30 | |
| 36 | 0% | Prepare Production Data | 5 days | Thu 10/07/04 | Wed 10/13/04 | ||
| 37 | 0% | Implement | 5 days | Thu 10/07/04 | Wed 10/13/04 | ||
| 38 | 0% | Workforce Planning Reports | 863 days | Thu 04/26/01 | Mon 08/16/04 | Balderson | |
| 39 | 0% | Develop Sub-Reports for Transfers, Promotions, & Demotions | 843 days | Thu 04/26/01 | Mon 07/19/04 | ||
| 40 | 0% | Requirements Definition | 843 days | Thu 04/26/01 | Mon 07/19/04 | ||
| 41 | 0% | Define and Document Requirements | 1 day | Mon 07/19/04 | Mon 07/19/04 | ||
| 42 | 0% | Obtain Approval - AHRS | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 43 | 0% | Analsyis & Design | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 44 | 0% | Perform Analysis | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 45 | 0% | Develop Specs | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 46 | 0% | Obtain Approval - AHRS | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 47 | 0% | Development | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 48 | 0% | Prepare Test Data | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 49 | 0% | Develop Programs | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 50 | 0% | Test Programs | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 51 | 0% | Obtain Approval - AHRS | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 52 | 0% | Implementation | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 53 | 0% | Prepare Production Data | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 54 | 0% | Move Programs to Production & SourceSafe | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 55 | 0% | Produce Faculty Demographics | 863 days | Thu 04/26/01 | Mon 08/16/04 | ||
| 56 | 0% | Requirements Definition | 863 days | Thu 04/26/01 | Mon 08/16/04 | ||
| 57 | 0% | Define and Document Requirements | 1 day | Mon 08/16/04 | Mon 08/16/04 | ||
| 58 | 0% | Obtain Approval - AHRS | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 59 | 0% | Analsyis & Design | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 60 | 0% | Perform Analysis | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 61 | 0% | Develop Specs | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 62 | 0% | Obtain Approval - AHRS | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 63 | 0% | Development | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 64 | 0% | Prepare Test Data | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 65 | 0% | Develop Programs | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 66 | 0% | Test Programs | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 67 | 0% | Obtain Approval - AHRS | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 68 | 0% | Implementation | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 69 | 0% | Prepare Production Data | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 70 | 0% | Move Programs to Production & SourceSafe | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 71 | 0% | Produce Turnover Summary Report (Includes All Categories) | 863 days | Thu 04/26/01 | Mon 08/16/04 | ||
| 72 | 0% | Requirements Definition | 863 days | Thu 04/26/01 | Mon 08/16/04 | ||
| 73 | 0% | Define and Document Requirements | 1 day | Mon 08/16/04 | Mon 08/16/04 | ||
| 74 | 0% | Obtain Approval - AHRS | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 75 | 0% | Analsyis & Design | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 76 | 0% | Perform Analysis | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 77 | 0% | Develop Specs | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 78 | 0% | Obtain Approval - AHRS | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 79 | 0% | Development | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 80 | 0% | Prepare Test Data | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 81 | 0% | Develop Programs | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 82 | 0% | Test Programs | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 83 | 0% | Obtain Approval - AHRS | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 84 | 0% | Implementation | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 85 | 0% | Prepare Production Data | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 86 | 0% | Move Programs to Production & SourceSafe | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 87 | 0% | EEO Assessment Projects | 1063 days | Thu 04/26/01 | Mon 05/23/05 | ||
| 88 | 0% | Add Appeals Module (ON HOLD until Entry of Appeals Available) | 36 days | Mon 04/04/05 | Mon 05/23/05 | Balderson | |
| 89 | 0% | System Analysis & Design Phase | 5 days | Mon 04/04/05 | Fri 04/08/05 | ||
| 90 | 0% | Develop Design / Specifications | 3 days | Mon 04/04/05 | Wed 04/06/05 | ||
| 91 | 0% | Review Specs with EES & Obtain signoff | 2 days | Thu 04/07/05 | Fri 04/08/05 | 90 | |
| 92 | 0% | Development Phase | 10 days | Mon 04/11/05 | Fri 04/22/05 | 89 | |
| 93 | 0% | Develop Programs | 4 days | Mon 04/11/05 | Thu 04/14/05 | ||
| 94 | 0% | Modify eeo_build_agency / Unit Test | 2 days | Fri 04/15/05 | Mon 04/18/05 | 93 | |
| 95 | 0% | Modify Stop Light Page & Statisitical Detail Page / Unit Test | 2 days | Tue 04/19/05 | Wed 04/20/05 | 94 | |
| 96 | 0% | Drill down / Unit Test | 2 days | Thu 04/21/05 | Fri 04/22/05 | 95 | |
| 97 | 0% | Test Phase | 18 days | Mon 04/25/05 | Wed 05/18/05 | 92 | |
| 98 | 0% | Develop Test Plan with Data Matrix | 2 days | Mon 04/25/05 | Tue 04/26/05 | ||
| 99 | 0% | Develop Test Data Based on Data Matrix | 4 days | Wed 04/27/05 | Mon 05/02/05 | 98 | |
| 100 | 0% | Develop Test Scripts | 4 days | Tue 05/03/05 | Fri 05/06/05 | 99 | |
| 101 | 0% | Execute Test Scripts | 4 days | Mon 05/09/05 | Thu 05/12/05 | 100 | |
| 102 | 0% | Perform Final Testing & Modifications, if Needed | 2 days | Fri 05/13/05 | Mon 05/16/05 | 101 | |
| 103 | 0% | Obtain Approval from OEES | 2 days | Tue 05/17/05 | Wed 05/18/05 | 102 | |
| 104 | 0% | Implementation Phase | 3 days | Thu 05/19/05 | Mon 05/23/05 | 97 | |
| 105 | 0% | Prepare Production Environment & Data | 2 days | Thu 05/19/05 | Fri 05/20/05 | ||
| 106 | 0% | Move Programs to Production & SafeSource | 1 day | Mon 05/23/05 | Mon 05/23/05 | 105 | |
| 107 | 0% | Add Training Module (ON HOLD until Training Data Available) | 36 days | Tue 01/04/05 | Tue 02/22/05 | Balderson | |
| 108 | 0% | System Analysis & Design Phase | 5 days | Tue 01/04/05 | Mon 01/10/05 | ||
| 109 | 0% | Develop Design / Specifications | 3 days | Tue 01/04/05 | Thu 01/06/05 | ||
| 110 | 0% | Review Specs with EES & Obtain signoff | 2 days | Fri 01/07/05 | Mon 01/10/05 | 109 | |
| 111 | 0% | Development Phase | 10 days | Tue 01/11/05 | Mon 01/24/05 | 108 | |
| 112 | 0% | Develop Programs | 4 days | Tue 01/11/05 | Fri 01/14/05 | ||
| 113 | 0% | Modify eeo_build_agency / Unit Test | 2 days | Mon 01/17/05 | Tue 01/18/05 | 112 | |
| 114 | 0% | Modify Stop Light Page & Statisitical Detail Page / Unit Test | 2 days | Wed 01/19/05 | Thu 01/20/05 | 113 | |
| 115 | 0% | Drill down / Unit Test | 2 days | Fri 01/21/05 | Mon 01/24/05 | 114 | |
| 116 | 0% | Test Phase | 18 days | Tue 01/25/05 | Thu 02/17/05 | 111 | |
| 117 | 0% | Develop Test Plan with Data Matrix | 2 days | Tue 01/25/05 | Wed 01/26/05 | ||
| 118 | 0% | Develop Test Data Based on Data Matrix | 4 days | Thu 01/27/05 | Tue 02/01/05 | 117 | |
| 119 | 0% | Develop Test Scripts | 4 days | Wed 02/02/05 | Mon 02/07/05 | 118 | |
| 120 | 0% | Execute Test Scripts | 4 days | Tue 02/08/05 | Fri 02/11/05 | 119 | |
| 121 | 0% | Perform Final Testing & Modifications, if Needed | 2 days | Mon 02/14/05 | Tue 02/15/05 | 120 | |
| 122 | 0% | Obtain Approval from OEES | 2 days | Wed 02/16/05 | Thu 02/17/05 | 121 | |
| 123 | 0% | Implementation Phase | 3 days | Fri 02/18/05 | Tue 02/22/05 | 116 | |
| 124 | 0% | Prepare Production Environment & Data | 2 days | Fri 02/18/05 | Mon 02/21/05 | ||
| 125 | 0% | Move Programs to Production & SafeSource | 1 day | Tue 02/22/05 | Tue 02/22/05 | 124 | |
| 126 | 0% | Add Written Notices Module (ON HOLD until after PMIS Development) | 1010 days | Thu 04/26/01 | Wed 03/09/05 | Balderson | |
| 127 | 0% | System Analysis & Design Phase | 1010 days | Thu 04/26/01 | Wed 03/09/05 | ||
| 128 | 0% | Develop Design / Specifications | 3 days | Mon 03/07/05 | Wed 03/09/05 | ||
| 129 | 0% | Review Specs with EES & Obtain signoff | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 130 | 0% | Development Phase | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 131 | 0% | Modify Programs | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 132 | 0% | Modify eeo_build_agency / Unit Test | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 133 | 0% | Modify Stop Light Page & Statisitical Detail Page / Unit Test | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 134 | 0% | Drill down / Unit Test | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 135 | 0% | Test Phase | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 136 | 0% | Develop Test Plan with Data Matrix | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 137 | 0% | Develop Test Data Based on Data Matrix | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 138 | 0% | Develop Test Scripts | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 139 | 0% | Execute Test Scripts | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 140 | 0% | Perform Final Testing & Modifications, if Needed | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 141 | 0% | Obtain Approval from OEES | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 142 | 0% | Implementation Phase | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 143 | 0% | Prepare Production Environment & Data | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 144 | 0% | Move Programs to Production & SafeSource | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 145 | 0% | EEO Compliance Calculator - Modification (on hold due to other priorities) | 860 days | Thu 04/26/01 | Wed 08/11/04 | Balderson | |
| 146 | 0% | System Analysis & Design Phase | 860 days | Thu 04/26/01 | Wed 08/11/04 | ||
| 147 | 0% | Modify Design / Specifications | 3 days | Mon 08/09/04 | Wed 08/11/04 | ||
| 148 | 0% | Review Specs with EES & Obtain signoff | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 149 | 0% | Development Phase | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 150 | 0% | Modify Programs | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 151 | 0% | Test Phase | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 152 | 0% | Develop Test Plan with Data Matrix | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 153 | 0% | Develop Test Data Based on Data Matrix | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 154 | 0% | Develop Test Scripts | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 155 | 0% | Execute Test Scripts | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 156 | 0% | Perform Final Testing & Modifications, if Needed | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 157 | 0% | Obtain Approval from OEES | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 158 | 0% | Implementation Phase | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 159 | 0% | Prepare Production Environment | 2 days | Thu 04/26/01 | Fri 04/27/01 | ||
| 160 | 0% | Move Programs to Production & SafeSource | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 161 | 0% | Modify Promotion, Lateral Transfer and New Hire Modules | 30 days | Tue 09/07/04 | Mon 10/18/04 | ||
| 162 | 0% | System Analysis & Design Phase | 5 days | Tue 09/07/04 | Mon 09/13/04 | ||
| 163 | 0% | Modify Design / Specifications | 3 days | Tue 09/07/04 | Thu 09/09/04 | ||
| 164 | 0% | Review Specs with EES & Obtain signoff | 2 days | Fri 09/10/04 | Mon 09/13/04 | 163 | |
| 165 | 0% | Development Phase | 4 days | Tue 09/14/04 | Fri 09/17/04 | 162 | |
| 166 | 0% | Modify Programs | 4 days | Tue 09/14/04 | Fri 09/17/04 | ||
| 167 | 0% | Test Phase | 18 days | Mon 09/20/04 | Wed 10/13/04 | 165 | |
| 168 | 0% | Develop Test Plan with Data Matrix | 2 days | Mon 09/20/04 | Tue 09/21/04 | ||
| 169 | 0% | Develop Test Data Based on Data Matrix | 4 days | Wed 09/22/04 | Mon 09/27/04 | 168 | |
| 170 | 0% | Develop Test Scripts | 4 days | Tue 09/28/04 | Fri 10/01/04 | 169 | |
| 171 | 0% | Execute Test Scripts | 4 days | Mon 10/04/04 | Thu 10/07/04 | 170 | |
| 172 | 0% | Perform Final Testing & Modifications, if Needed | 2 days | Fri 10/08/04 | Mon 10/11/04 | 171 | |
| 173 | 0% | Obtain Approval from OEES | 2 days | Tue 10/12/04 | Wed 10/13/04 | 172 | |
| 174 | 0% | Implementation Phase | 3 days | Thu 10/14/04 | Mon 10/18/04 | 167 | |
| 175 | 0% | Prepare Production Environment & Data | 2 days | Thu 10/14/04 | Fri 10/15/04 | ||
| 176 | 0% | Move Programs to Production & SafeSource | 1 day | Mon 10/18/04 | Mon 10/18/04 | 175 | |
| 177 | 0% | Modification - Display All Detailed Records behind Link | 899 days | Thu 04/26/01 | Tue 10/05/04 | ||
| 178 | 0% | Perform Analysis | 2 days | Mon 10/04/04 | Tue 10/05/04 | ||
| 179 | 0% | Modify / Test Programs | 4 days | Thu 04/26/01 | Tue 05/01/01 | ||
| 180 | 0% | Implement in Production | 1 day | Thu 04/26/01 | Thu 04/26/01 | ||
| 181 | 0% | Written Notices - Process to Load EEO Assessment (ON HOLD) | 13 days | Thu 04/26/01 | Mon 05/14/01 | Balderson | |
| 182 | 0% | Requirements Definition | 3 days | Thu 04/26/01 | Mon 04/30/01 | ||
| 183 | 0% | Analsyis & Design | 9 days | Thu 04/26/01 | Tue 05/08/01 | ||
| 184 | 0% | Development | 13 days | Thu 04/26/01 | Mon 05/14/01 | ||
| 185 | 0% | Implementation | 3 days | Thu 04/26/01 | Mon 04/30/01 | ||
| 186 | 14% | Applicant Flow - Automation of Error Notification | 19 days | Wed 06/23/04 | Mon 07/19/04 | Balderson | |
| 187 | 100% | Requirements Definition | 2 days | Wed 06/23/04 | Thu 06/24/04 | ||
| 188 | 100% | Define and Document Requirements | 1 day | Wed 06/23/04 | Wed 06/23/04 | Balderson | |
| 189 | 100% | Obtain Approval - AHRS | 1 day | Thu 06/24/04 | Thu 06/24/04 | 188 | Barnes-Hargress |
| 190 | 0% | Analsyis & Design (On Hold Due to Other Priorities) | 3 days | Fri 06/25/04 | Tue 06/29/04 | 187 | |
| 191 | 0% | Perform Analysis | 1 day | Fri 06/25/04 | Fri 06/25/04 | Balderson | |
| 192 | 0% | Develop Specs | 1 day | Mon 06/28/04 | Mon 06/28/04 | 191 | Balderson |
| 193 | 0% | Obtain Approval - AHRS | 1 day | Tue 06/29/04 | Tue 06/29/04 | 192 | Barnes-Hargress |
| 194 | 8% | Development | 11 days | Wed 06/30/04 | Wed 07/14/04 | 190 | |
| 195 | 0% | Develop email Message Template | 1 day | Wed 06/30/04 | Wed 06/30/04 | Balderson | |
| 196 | 100% | Develop Database to Retain Applicant Flow Contact Data | 1 day | Wed 06/30/04 | Wed 06/30/04 | Paul | |
| 197 | 0% | Prepare Test Data | 2 days | Wed 06/30/04 | Thu 07/01/04 | Andersen | |
| 198 | 0% | Develop Process for email Submission | 3 days | Fri 07/02/04 | Tue 07/06/04 | 197 | Andersen |
| 199 | 0% | Develop Programs | 3 days | Wed 07/07/04 | Fri 07/09/04 | 198 | Andersen |
| 200 | 0% | Test Application & Process | 2 days | Mon 07/12/04 | Tue 07/13/04 | 199 | Andersen,Balderson |
| 201 | 0% | Obtain Approval - AHRS | 1 day | Wed 07/14/04 | Wed 07/14/04 | 200 | Barnes-Hargress |
| 202 | 0% | Implementation | 3 days | Thu 07/15/04 | Mon 07/19/04 | 194 | |
| 203 | 0% | Prepare Production Data | 2 days | Thu 07/15/04 | Fri 07/16/04 | Andersen | |
| 204 | 0% | Move Programs to Production and SourceSafe | 1 day | Mon 07/19/04 | Mon 07/19/04 | 203 | Andersen |
| 205 | 0% | Salary Reference - Add New Surveys (waiting on a different type of files from the vendor) | 15 days | Mon 09/27/04 | Fri 10/15/04 | Balderson | |
| 206 | 0% | Analsyis & Design | 4 days | Mon 09/27/04 | Thu 09/30/04 | ||
| 207 | 0% | Perform Analysis | 2 days | Mon 09/27/04 | Tue 09/28/04 | ||
| 208 | 0% | Develop Specs | 1 day | Wed 09/29/04 | Wed 09/29/04 | 207 | |
| 209 | 0% | Obtain Approval - AHRS | 1 day | Thu 09/30/04 | Thu 09/30/04 | 208 | |
| 210 | 0% | Development | 9 days | Fri 10/01/04 | Wed 10/13/04 | 206 | |
| 211 | 0% | Modify Programs | 6 days | Fri 10/01/04 | Fri 10/08/04 | ||
| 212 | 0% | Test Application | 2 days | Mon 10/11/04 | Tue 10/12/04 | 211 | |
| 213 | 0% | Obtain Approval - AHRS | 1 day | Wed 10/13/04 | Wed 10/13/04 | 212 | |
| 214 | 0% | Implementation | 2 days | Thu 10/14/04 | Fri 10/15/04 | 210 | |
| 215 | 0% | Prepare Production Data | 1 day | Thu 10/14/04 | Thu 10/14/04 | ||
| 216 | 0% | Move Programs to Production and SourceSafe | 1 day | Fri 10/15/04 | Fri 10/15/04 | 215 | |
| 217 | 0% | VRS Retirement Service Reporting (waiting on business requirements) | 49 days | Mon 08/09/04 | Thu 10/14/04 | Balderson | |
| 218 | 0% | Requirements Definition | 6 days | Mon 08/09/04 | Mon 08/16/04 | ||
| 219 | 0% | Identify and Document Requirements | 4 days | Mon 08/09/04 | Thu 08/12/04 | ||
| 220 | 0% | Obtain Approval from AHRS | 2 days | Fri 08/13/04 | Mon 08/16/04 | 219 | |
| 221 | 0% | Analysis and Design Phases | 11 days | Tue 08/17/04 | Tue 08/31/04 | 218 | |
| 222 | 0% | Perform Analysis | 5 days | Tue 08/17/04 | Mon 08/23/04 | ||
| 223 | 0% | Develop Design & Specifications | 4 days | Tue 08/24/04 | Fri 08/27/04 | 222 | |
| 224 | 0% | Review Specs with AHRS & Obtain Approval | 2 days | Mon 08/30/04 | Tue 08/31/04 | 223 | |
| 225 | 0% | Development Phase | 29 days | Wed 09/01/04 | Mon 10/11/04 | 221 | |
| 226 | 0% | Prepare Test Environment & Data | 2 days | Wed 09/01/04 | Thu 09/02/04 | ||
| 227 | 0% | Develop Interface | 4 days | Fri 09/03/04 | Wed 09/08/04 | 226 | |
| 228 | 0% | Develop Progams / Unit Test | 6 days | Thu 09/09/04 | Thu 09/16/04 | 227 | |
| 229 | 0% | Develop Test Plan | 3 days | Fri 09/17/04 | Tue 09/21/04 | 228 | |
| 230 | 0% | Develop Test Scripts | 5 days | Wed 09/22/04 | Tue 09/28/04 | 229 | |
| 231 | 0% | Perform System Testing | 5 days | Wed 09/29/04 | Tue 10/05/04 | 230 | |
| 232 | 0% | Update System Documentation | 2 days | Wed 10/06/04 | Thu 10/07/04 | 231 | |
| 233 | 0% | Obtain Approval | 2 days | Fri 10/08/04 | Mon 10/11/04 | 232 | |
| 234 | 0% | Implementation | 3 days | Tue 10/12/04 | Thu 10/14/04 | 225 | |
| 235 | 0% | Prepare Production Environment & Data Files | 2 days | Tue 10/12/04 | Wed 10/13/04 | ||
| 236 | 0% | Move programs to Production and SafeSource | 1 day | Thu 10/14/04 | Thu 10/14/04 | 235 | |
| 237 | 0% | CIPPS Leave Data Reporting (waiting on business requirements) | 49 days | Mon 09/13/04 | Thu 11/18/04 | Balderson | |
| 238 | 0% | Requirements Definition | 6 days | Mon 09/13/04 | Mon 09/20/04 | ||
| 239 | 0% | Identify and Document Requirements | 4 days | Mon 09/13/04 | Thu 09/16/04 | ||
| 240 | 0% | Obtain Approval from AHRS | 2 days | Fri 09/17/04 | Mon 09/20/04 | 239 | |
| 241 | 0% | Analysis and Design Phases | 11 days | Tue 09/21/04 | Tue 10/05/04 | 238 | |
| 242 | 0% | Perform Analysis | 5 days | Tue 09/21/04 | Mon 09/27/04 | ||
| 243 | 0% | Develop Design & Specifications | 4 days | Tue 09/28/04 | Fri 10/01/04 | 242 | |
| 244 | 0% | Review Specs with AHRS & Obtain Approval | 2 days | Mon 10/04/04 | Tue 10/05/04 | 243 | |
| 245 | 0% | Development Phase | 29 days | Wed 10/06/04 | Mon 11/15/04 | 241 | |
| 246 | 0% | Prepare Test Environment & Data | 2 days | Wed 10/06/04 | Thu 10/07/04 | ||
| 247 | 0% | Develop Interface | 4 days | Fri 10/08/04 | Wed 10/13/04 | 246 | |
| 248 | 0% | Develop Progams / Unit Test | 6 days | Thu 10/14/04 | Thu 10/21/04 | 247 | |
| 249 | 0% | Develop Test Plan | 3 days | Fri 10/22/04 | Tue 10/26/04 | 248 | |
| 250 | 0% | Develop Test Scripts | 5 days | Wed 10/27/04 | Tue 11/02/04 | 249 | |
| 251 | 0% | Perform System Testing | 5 days | Wed 11/03/04 | Tue 11/09/04 | 250 | |
| 252 | 0% | Update System Documentation | 2 days | Wed 11/10/04 | Thu 11/11/04 | 251 | |
| 253 | 0% | Obtain Approval | 2 days | Fri 11/12/04 | Mon 11/15/04 | 252 | |
| 254 | 0% | Implementation | 3 days | Tue 11/16/04 | Thu 11/18/04 | 245 | |
| 255 | 0% | Prepare Production Environment Data Files | 2 days | Tue 11/16/04 | Wed 11/17/04 | ||
| 256 | 0% | Move programs to Production and SafeSource | 1 day | Thu 11/18/04 | Thu 11/18/04 | 255 | |
| 2 | 38% | SQL Server Projects | 584.88 days | Mon 02/03/03 | Fri 04/29/05 | ||
| 3 | 0% | Recruit File Loader Layout | 17 days | Mon 09/01/03 | Tue 09/23/03 | Bradley Paul | |
| 1 | 0% | Recruit File Loader Layout Change | 17 days | Mon 09/01/03 | Tue 09/23/03 | ||
| 2 | 0% | Requirements Definition | 1 day | Mon 09/01/03 | Mon 09/01/03 | ||
| 3 | 0% | Analysis | 5 days | Tue 09/02/03 | Mon 09/08/03 | 2 | |
| 4 | 0% | Design | 5 days | Tue 09/09/03 | Mon 09/15/03 | 3 | |
| 5 | 0% | Code | 5 days | Tue 09/16/03 | Mon 09/22/03 | 4 | |
| 6 | 0% | Implement | 1 day | Tue 09/23/03 | Tue 09/23/03 | 5 | |
| 4 | 0% | Password Encryption to Access Legacy Systems | 50 days | Fri 08/13/04 | Thu 10/21/04 | Bradley Paul | |
| 1 | 0% | Encryption of BES/PMIS passwords | 50 days | Fri 08/13/04 | Thu 10/21/04 | ||
| 2 | 0% | Requirements | 10 days | Fri 08/13/04 | Thu 08/26/04 | ||
| 3 | 0% | Analysis | 10 days | Fri 08/27/04 | Thu 09/09/04 | 2 | |
| 4 | 0% | Design | 10 days | Fri 09/10/04 | Thu 09/23/04 | 3 | |
| 5 | 0% | Code | 10 days | Fri 09/24/04 | Thu 10/07/04 | 4 | |
| 6 | 0% | Implementation | 10 days | Fri 10/08/04 | Thu 10/21/04 | 5 | |
| 5 | 41% | Security Wrapper | 327 days | Mon 09/01/03 | Tue 11/30/04 | Bradley Paul | |
| 1 | 82% | Security Wrapper Upgrade (Phase 1 - conversion from UNIX) | 325 days | Wed 09/03/03 | Tue 11/30/04 | ||
| 2 | 100% | Project Definition | 2 days | Mon 01/12/04 | Tue 01/13/04 | ||
| 3 | 100% | Requirements Definition | 60 days | Wed 09/03/03 | Tue 11/25/03 | 2 | |
| 4 | 100% | Alternatives and Recommendations | 5 days | Wed 11/26/03 | Tue 12/02/03 | 3 | |
| 5 | 100% | Design | 90 days | Wed 12/03/03 | Tue 04/06/04 | 4 | |
| 6 | 92% | Development | 120 days | Wed 04/07/04 | Tue 09/21/04 | 5 | |
| 7 | 0% | Implementation | 20 days | Wed 09/22/04 | Tue 10/19/04 | 6 | |
| 8 | 0% | Evaluation | 30 days | Wed 10/20/04 | Tue 11/30/04 | 7 | |
| 9 | 0% | Security Wrapper Upgrade (Phase 2 - file level security) | 327 days | Mon 09/01/03 | Tue 11/30/04 | ||
| 10 | 0% | Project Definition | 2 days | Mon 09/01/03 | Tue 09/02/03 | ||
| 11 | 0% | Requirements Definition | 60 days | Wed 09/03/03 | Tue 11/25/03 | 10 | |
| 12 | 0% | Alternatives and Recommendations | 5 days | Wed 11/26/03 | Tue 12/02/03 | 11 | |
| 13 | 0% | Design | 90 days | Wed 12/03/03 | Tue 04/06/04 | 12 | |
| 14 | 0% | Development | 120 days | Wed 04/07/04 | Tue 09/21/04 | 13 | |
| 15 | 0% | Implementation | 20 days | Wed 09/22/04 | Tue 10/19/04 | 14 | |
| 16 | 0% | Evaluation | 30 days | Wed 10/20/04 | Tue 11/30/04 | 15 | |
| 6 | 17% | Enterprise Mitem Upgrade (Flexible framework to add applications and pools) | 187 days | Mon 08/02/04 | Tue 04/19/05 | Bradley Paul | |
| 1 | 17% | Enterprise Mitem V.2 | 187 days | Mon 08/02/04 | Tue 04/19/05 | ||
| 2 | 100% | Project Definition | 2 days | Mon 08/02/04 | Tue 08/03/04 | ||
| 3 | 100% | Requirements Definition | 30 days | Wed 08/04/04 | Tue 09/14/04 | 2 | |
| 4 | 0% | Alternatives and Recommendations | 5 days | Wed 09/15/04 | Tue 09/21/04 | 3 | |
| 5 | 0% | Design | 60 days | Wed 09/22/04 | Tue 12/14/04 | 4 | |
| 6 | 0% | Development | 60 days | Wed 12/15/04 | Tue 03/08/05 | 5 | |
| 7 | 0% | Implementation | 10 days | Wed 03/09/05 | Tue 03/22/05 | 6 | |
| 8 | 0% | Evaluation | 20 days | Wed 03/23/05 | Tue 04/19/05 | 7 | |
| 7 | 78% | ITech Client/Server environment Migration and Reorganization | 459.75 days | Mon 03/03/03 | Fri 12/03/04 | ||
| 1 | 83% | NT Server Configuration and Data Reorganization | 454.75 days | Mon 03/10/03 | Fri 12/03/04 | Bradley Paul,Allen Kass | |
| 2 | 100% | Requirements Definition | 60 days | Mon 03/10/03 | Fri 05/30/03 | ||
| 3 | 100% | Planning Phase | 20 days | Mon 04/21/03 | Fri 05/16/03 | 2 | |
| 4 | 80% | Implementation Phase | 400 days | Mon 05/19/03 | Fri 11/26/04 | 3 | |
| 5 | 5% | Review Phase | 5 days | Mon 06/30/03 | Fri 12/03/04 | 4 | |
| 6 | 100% | SAS migration from UNIX to NT | 60 days | Mon 03/03/03 | Fri 05/23/03 | Keith Andersen | |
| 7 | 100% | Analysis | 10 days | Mon 03/03/03 | Fri 03/14/03 | ||
| 8 | 100% | Servers configuration | 5 days | Mon 03/17/03 | Fri 03/21/03 | 7 | |
| 9 | 100% | Data/Programs Migration | 35 days | Mon 03/24/03 | Fri 05/09/03 | 8 | |
| 10 | 100% | Testing | 5 days | Mon 05/12/03 | Fri 05/16/03 | 9 | |
| 11 | 100% | Implementation | 5 days | Mon 05/19/03 | Fri 05/23/03 | 10 | |
| 12 | 69% | Apache Migration | 120 days | Mon 04/05/04 | Fri 09/17/04 | Bradley Paul,Allen Kass | |
| 13 | 100% | Migrate Static Pages | 20 days | Mon 04/05/04 | Fri 04/30/04 | ||
| 14 | 63% | Migrate Dynamic Pages with CGI | 100 days | Mon 05/03/04 | Fri 09/17/04 | 13 | |
| 15 | 0% | Script Migration | 23 days | Mon 03/03/03 | Wed 04/02/03 | Bradley Paul,Allen Kass | |
| 16 | 0% | Identification of Scripts to Migrate or Rewrite | 3 days | Mon 03/03/03 | Wed 03/05/03 | ||
| 17 | 0% | Migration | 5 days | Thu 03/06/03 | Wed 03/12/03 | 16 | |
| 18 | 0% | Rewrite | 15 days | Thu 03/13/03 | Wed 04/02/03 | 17 | |
| 19 | 0% | Scheduler Migration | 6 days | Mon 03/03/03 | Mon 03/10/03 | Bradley Paul,Allen Kass | |
| 20 | 0% | Planning | 1 day | Mon 03/03/03 | Mon 03/03/03 | ||
| 21 | 0% | Implementation | 5 days | Tue 03/04/03 | Mon 03/10/03 | 20 | |
| 8 | 20% | File distribution by agency folders (File split) | 421 days | Fri 02/07/03 | Fri 09/17/04 | Bradley Paul | |
| 9 | 100% | Requirements Definition | 60 days | Wed 09/03/03 | Tue 11/25/03 | ||
| 10 | 0% | Design | 90 days | Wed 11/26/03 | Tue 03/30/04 | 9 | |
| 11 | 0% | Development | 120 days | Wed 03/31/04 | Tue 09/14/04 | 10 | |
| 12 | 0% | Test | 3 days | Wed 09/15/04 | Fri 09/17/04 | 11 | |
| 13 | 0% | Implementation | 20 days | Fri 02/07/03 | Thu 03/06/03 | ||
| 14 | 19% | File Repository (secure FTP and NAS setup) | 315 days | Wed 09/03/03 | Tue 11/16/04 | Bradley Paul | |
| 15 | 100% | Requirements Definition | 60 days | Wed 09/03/03 | Tue 11/25/03 | ||
| 16 | 0% | Design | 90 days | Wed 11/26/03 | Tue 03/30/04 | 15 | |
| 17 | 0% | Development | 120 days | Wed 03/31/04 | Tue 09/14/04 | 16 | |
| 18 | 0% | Test | 25 days | Wed 09/15/04 | Tue 10/19/04 | 17 | |
| 19 | 0% | Implementation | 20 days | Wed 10/20/04 | Tue 11/16/04 | 18 | |
| 20 | 100% | File Upload Upgrade for Windows/Sql environment | 5 days | Mon 03/03/03 | Fri 03/07/03 | Bradley Paul | |
| 1 | 100% | File Upload Rewrite | 5 days | Mon 03/03/03 | Fri 03/07/03 | ||
| 21 | 5% | Recruit Notification / Adjustments | 10 days | Mon 03/03/03 | Fri 03/14/03 | Bradley Paul | |
| 1 | 5% | Recruit Notification | 10 days | Mon 03/03/03 | Fri 03/14/03 | ||
| 22 | 28% | VIPERS Interface - PHASE I | 145.88 days | Fri 10/08/04 | Fri 04/29/05 | ||
| 1 | 100% | Project Planning | 3 days | Fri 10/08/04 | Tue 10/12/04 | ||
| 2 | 74% | BES | 5 days | Wed 10/13/04 | Tue 10/19/04 | 1 | |
| 3 | 100% | Requirements | 1 day | Wed 10/13/04 | Wed 10/13/04 | Brenda Farrish | |
| 4 | 100% | Design | 1 day | Thu 10/14/04 | Thu 10/14/04 | 3 | David Savanyu |
| 5 | 100% | Code | 1 day | Fri 10/15/04 | Fri 10/15/04 | 4 | David Savanyu |
| 6 | 70% | Test | 1 day | Mon 10/18/04 | Mon 10/18/04 | 5 | Brenda Farrish |
| 7 | 0% | Implementation | 1 day | Tue 10/19/04 | Tue 10/19/04 | 6 | David Savanyu |
| 8 | 100% | Mitem - UNISYS | 24.88 days | Wed 10/20/04 | Wed 11/24/04 | 2,70 | |
| 9 | 100% | Patterns | 5.75 days | Wed 10/20/04 | Thu 10/28/04 | ||
| 10 | 100% | Identify | 1.25 days | Wed 10/20/04 | Fri 10/22/04 | Bradley Paul[80%] | |
| 11 | 100% | Plan | 1.25 days | Fri 10/22/04 | Mon 10/25/04 | 10 | Bradley Paul[80%] |
| 12 | 100% | Create | 1.25 days | Mon 10/25/04 | Tue 10/26/04 | 11 | Bradley Paul[80%] |
| 13 | 100% | Test | 1.25 days | Wed 10/27/04 | Thu 10/28/04 | 12 | Bradley Paul[80%] |
| 14 | 100% | Maps | 5.13 days | Thu 10/28/04 | Thu 11/04/04 | 9 | |
| 15 | 100% | Identify | 1.25 days | Thu 10/28/04 | Mon 11/01/04 | Bradley Paul[80%] | |
| 16 | 100% | Plan | 1.25 days | Mon 11/01/04 | Tue 11/02/04 | 15 | Bradley Paul[80%] |
| 17 | 100% | Create | 1.25 days | Tue 11/02/04 | Wed 11/03/04 | 16 | Bradley Paul[80%] |
| 18 | 100% | Test | 1 day | Wed 11/03/04 | Thu 11/04/04 | 17 | Bradley Paul[80%] |
| 19 | 100% | Groups | 4 days | Thu 11/04/04 | Wed 11/10/04 | 14 | |
| 20 | 100% | Identify | 1 day | Thu 11/04/04 | Fri 11/05/04 | Bradley Paul[80%] | |
| 21 | 100% | Plan | 1 day | Fri 11/05/04 | Mon 11/08/04 | 20 | Bradley Paul[80%] |
| 22 | 100% | Create | 1 day | Mon 11/08/04 | Tue 11/09/04 | 21 | Bradley Paul[80%] |
| 23 | 100% | Test | 1 day | Tue 11/09/04 | Wed 11/10/04 | 22 | Bradley Paul[80%] |
| 24 | 100% | Containers | 4 days | Wed 11/10/04 | Tue 11/16/04 | 19 | |
| 25 | 100% | Identify | 1 day | Wed 11/10/04 | Thu 11/11/04 | Bradley Paul[80%] | |
| 26 | 100% | Plan | 1 day | Thu 11/11/04 | Fri 11/12/04 | 25 | Bradley Paul[80%] |
| 27 | 100% | Create | 1 day | Fri 11/12/04 | Mon 11/15/04 | 26 | Bradley Paul[80%] |
| 28 | 100% | Test | 1 day | Mon 11/15/04 | Tue 11/16/04 | 27 | Bradley Paul[80%] |
| 29 | 100% | Handlers | 6 days | Tue 11/16/04 | Wed 11/24/04 | 24 | |
| 30 | 100% | Identify | 1 day | Tue 11/16/04 | Wed 11/17/04 | Bradley Paul[80%] | |
| 31 | 100% | Plan | 1 day | Wed 11/17/04 | Thu 11/18/04 | 30 | Bradley Paul[80%] |
| 32 | 100% | Create | 3 days | Thu 11/18/04 | Tue 11/23/04 | 31 | Bradley Paul[80%] |
| 33 | 100% | Test | 1 day | Tue 11/23/04 | Wed 11/24/04 | 32 | Bradley Paul[80%] |
| 34 | 0% | VIPERS Program Flow | 46 days | Wed 10/13/04 | Wed 12/15/04 | 1 | |
| 35 | 0% | Identify VIPERS Flow | 1 day | Wed 10/13/04 | Wed 10/13/04 | VRS / DHRM | |
| 36 | 0% | Document VIPERS Flow | 5 days | Thu 12/09/04 | Wed 12/15/04 | 35 | VRS / DHRM |
| 37 | 9% | Mitem - IBM | 70.38 days | Wed 11/24/04 | Wed 03/02/05 | 34,8 | |
| 38 | 100% | Setup Base Application | 7 days | Wed 11/24/04 | Fri 12/03/04 | ||
| 39 | 100% | Requirements | 1 day | Wed 11/24/04 | Mon 11/29/04 | Bradley Paul[80%] | |
| 40 | 100% | Design | 1 day | Mon 11/29/04 | Tue 11/30/04 | 39 | Bradley Paul[80%] |
| 41 | 100% | Code | 1 day | Tue 11/30/04 | Wed 12/01/04 | 40 | Bradley Paul[80%] |
| 42 | 100% | Test | 1 day | Wed 12/01/04 | Thu 12/02/04 | 41 | Bradley Paul[80%] |
| 43 | 100% | Implementation | 1 day | Thu 12/02/04 | Fri 12/03/04 | 42 | Bradley Paul[80%] |
| 44 | 0% | Brad Unavailable | 21 days | Thu 12/16/04 | Thu 01/13/05 | 43 | |
| 45 | 0% | Patterns | 3.88 days | Tue 01/18/05 | Fri 01/21/05 | 44 | |
| 46 | 0% | Identify | 1 day | Tue 01/18/05 | Tue 01/18/05 | Bradley Paul[80%] | |
| 47 | 0% | Plan | 1 day | Wed 01/19/05 | Wed 01/19/05 | 46 | Bradley Paul[80%] |
| 48 | 0% | Create | 1 day | Thu 01/20/05 | Thu 01/20/05 | 47 | Bradley Paul[80%] |
| 49 | 0% | Test | 1 day | Fri 01/21/05 | Fri 01/21/05 | 48 | Bradley Paul[80%] |
| 50 | 0% | Maps | 3.88 days | Mon 01/24/05 | Thu 01/27/05 | 45 | |
| 51 | 0% | Identify | 1 day | Mon 01/24/05 | Mon 01/24/05 | Bradley Paul[80%] | |
| 52 | 0% | Plan | 1 day | Tue 01/25/05 | Tue 01/25/05 | 51 | Bradley Paul[80%] |
| 53 | 0% | Create | 1 day | Wed 01/26/05 | Wed 01/26/05 | 52 | Bradley Paul[80%] |
| 54 | 0% | Test | 1 day | Thu 01/27/05 | Thu 01/27/05 | 53 | Bradley Paul[80%] |
| 55 | 0% | Groups | 3.88 days | Fri 01/28/05 | Wed 02/02/05 | 50 | |
| 56 | 0% | Identify | 1 day | Fri 01/28/05 | Fri 01/28/05 | Bradley Paul[80%] | |
| 57 | 0% | Plan | 1 day | Mon 01/31/05 | Mon 01/31/05 | 56 | Bradley Paul[80%] |
| 58 | 0% | Create | 1 day | Tue 02/01/05 | Tue 02/01/05 | 57 | Bradley Paul[80%] |
| 59 | 0% | Test | 1 day | Wed 02/02/05 | Wed 02/02/05 | 58 | Bradley Paul[80%] |
| 60 | 0% | Containers | 3.88 days | Thu 02/03/05 | Tue 02/08/05 | 55 | |
| 61 | 0% | Identify | 1 day | Thu 02/03/05 | Thu 02/03/05 | Bradley Paul[80%] | |
| 62 | 0% | Plan | 1 day | Fri 02/04/05 | Fri 02/04/05 | 61 | Bradley Paul[80%] |
| 63 | 0% | Create | 1 day | Mon 02/07/05 | Mon 02/07/05 | 62 | Bradley Paul[80%] |
| 64 | 0% | Test | 1 day | Tue 02/08/05 | Tue 02/08/05 | 63 | Bradley Paul[80%] |
| 65 | 0% | Handlers | 15.88 days | Wed 02/09/05 | Wed 03/02/05 | 60 | |
| 66 | 0% | Identify | 1 day | Wed 02/09/05 | Wed 02/09/05 | Bradley Paul[80%] | |
| 67 | 0% | Plan | 2 days | Thu 02/10/05 | Fri 02/11/05 | 66 | Bradley Paul[80%] |
| 68 | 0% | Create | 10 days | Mon 02/14/05 | Fri 02/25/05 | 67 | Bradley Paul[80%] |
| 69 | 0% | Test | 3 days | Mon 02/28/05 | Wed 03/02/05 | 68 | Bradley Paul[80%] |
| 70 | 80% | Conversion Class | 5.63 days | Wed 10/13/04 | Wed 10/20/04 | 1 | |
| 71 | 100% | Requirements | 1 day | Wed 10/13/04 | Thu 10/14/04 | Bradley Paul[80%] | |
| 72 | 100% | Design | 1 day | Thu 10/14/04 | Fri 10/15/04 | 71 | Bradley Paul[80%] |
| 73 | 100% | Code | 1 day | Fri 10/15/04 | Mon 10/18/04 | 72 | Bradley Paul[80%] |
| 74 | 100% | Test | 1 day | Mon 10/18/04 | Tue 10/19/04 | 73 | Bradley Paul[80%] |
| 75 | 0% | Implementation | 1 day | Tue 10/19/04 | Wed 10/20/04 | 74 | Bradley Paul[80%] |
| 76 | 0% | E-Direct | 20 days | Wed 03/02/05 | Wed 03/30/05 | 8,37,70 | |
| 77 | 0% | Screen Changes | 5 days | Wed 03/02/05 | Wed 03/09/05 | ||
| 78 | 0% | Requirements | 1 day | Wed 03/02/05 | Thu 03/03/05 | Brenda Farrish | |
| 79 | 0% | Design | 1 day | Fri 03/04/05 | Fri 03/04/05 | 78 | Bradley Paul[80%] |
| 80 | 0% | Code | 1 day | Mon 03/07/05 | Mon 03/07/05 | 79 | Bradley Paul[80%] |
| 81 | 0% | Test | 1 day | Tue 03/08/05 | Tue 03/08/05 | 80 | Bradley Paul[80%] |
| 82 | 0% | Implementation | 1 day | Wed 03/09/05 | Wed 03/09/05 | 81 | Bradley Paul[80%] |
| 83 | 0% | VIPERS Module | 4.88 days | Thu 03/10/05 | Wed 03/16/05 | 77 | |
| 84 | 0% | Requirements | 1 day | Thu 03/10/05 | Thu 03/10/05 | Bradley Paul[80%] | |
| 85 | 0% | Design | 1 day | Fri 03/11/05 | Fri 03/11/05 | 84 | Bradley Paul[80%] |
| 86 | 0% | Code | 1 day | Mon 03/14/05 | Mon 03/14/05 | 85 | Bradley Paul[80%] |
| 87 | 0% | Test | 1 day | Tue 03/15/05 | Tue 03/15/05 | 86 | Bradley Paul[80%] |
| 88 | 0% | Implementation | 1 day | Wed 03/16/05 | Wed 03/16/05 | 87 | Bradley Paul[80%] |
| 89 | 0% | Integration of VIPERS Module | 9.88 days | Thu 03/17/05 | Wed 03/30/05 | 83 | |
| 90 | 0% | Requirements | 1 day | Thu 03/17/05 | Thu 03/17/05 | Bradley Paul[80%] | |
| 91 | 0% | Design | 1 day | Fri 03/18/05 | Fri 03/18/05 | 90 | Bradley Paul[80%] |
| 92 | 0% | Code | 5 days | Mon 03/21/05 | Fri 03/25/05 | 91 | Bradley Paul[80%] |
| 93 | 0% | Test | 2 days | Mon 03/28/05 | Tue 03/29/05 | 92 | Bradley Paul[80%] |
| 94 | 0% | Implementation | 1 day | Wed 03/30/05 | Wed 03/30/05 | 93 | Bradley Paul[80%] |
| 95 | 0% | System Test | 13 days | Wed 03/30/05 | Mon 04/18/05 | 76 | |
| 96 | 0% | Create Test Scripts | 3 days | Wed 03/30/05 | Mon 04/04/05 | Brenda Farrish | |
| 97 | 0% | Define Testers | 1 day | Mon 04/04/05 | Tue 04/05/05 | 96 | Brenda Farrish |
| 98 | 0% | Test | 8 days | Tue 04/05/05 | Fri 04/15/05 | 97 | |
| 99 | 0% | Document Test Results | 1 day | Fri 04/15/05 | Mon 04/18/05 | 98 | Brenda Farrish |
| 100 | 0% | Debugging | 6.88 days | Tue 04/19/05 | Wed 04/27/05 | 95 | |
| 101 | 0% | Analyse Problems | 1 day | Tue 04/19/05 | Tue 04/19/05 | Bradley Paul[80%] | |
| 102 | 0% | Design Code Adjustments | 1 day | Wed 04/20/05 | Wed 04/20/05 | 101 | Bradley Paul[80%] |
| 103 | 0% | Code Bug Fixes | 5 days | Thu 04/21/05 | Wed 04/27/05 | 102 | Bradley Paul[80%] |
| 104 | 0% | Implementation | 1.88 days | Thu 04/28/05 | Fri 04/29/05 | 100 | |
| 105 | 0% | Plan | 1 day | Thu 04/28/05 | Thu 04/28/05 | Bradley Paul[80%] | |
| 106 | 0% | Implement System | 1 day | Fri 04/29/05 | Fri 04/29/05 | 105 | Bradley Paul[80%] |
| 23 | 0% | E-Direct annual upgrades (Maintenance) | 20 days | Mon 02/03/03 | Fri 02/28/03 | Bradley Paul | |
| 1 | 0% | E-Direct V.2 | 20 days | Mon 02/03/03 | Fri 02/28/03 | Michelle Thompson | |
| 24 | 0% | Special Projects | 745 days | Fri 02/07/03 | Thu 12/15/05 | ||
| 25 | 0% | EEO-4 Web Reporting Tool (Phase II) | 96 days | Thu 08/04/05 | Thu 12/15/05 | Mary Phythian | |
| 26 | 0% | Requirements Definition | 2 days | Thu 08/04/05 | Fri 08/05/05 | ||
| 27 | 0% | Identify User Requirements | 1 day | Thu 08/04/05 | Thu 08/04/05 | Phythian[50%],Osei[50%] | |
| 28 | 0% | Identify Security Requirements | 1 day | Fri 08/05/05 | Fri 08/05/05 | 27 | Phythian[75%] |
| 29 | 0% | System Analysis and Design | 1 day | Mon 08/08/05 | Mon 08/08/05 | 26 | |
| 30 | 0% | Develop Design & Specifications | 1 day | Mon 08/08/05 | Mon 08/08/05 | Mary Phythian | |
| 31 | 0% | Development | 9 days | Tue 08/09/05 | Fri 08/19/05 | 29 | |
| 32 | 0% | Develop SAS Program - Production of EEO-4 Agency Report | 8 days | Tue 08/09/05 | Thu 08/18/05 | Mary Phythian[85%],Keith Andersen[15%] | |
| 33 | 0% | Execute Tests in Development | 1 day | Fri 08/19/05 | Fri 08/19/05 | 32 | Mary Phythian |
| 34 | 0% | System Testing | 3 days | Fri 12/09/05 | Tue 12/13/05 | ||
| 35 | 0% | Move files to Test | 1 day | Fri 12/09/05 | Fri 12/09/05 | Mary Phythian | |
| 36 | 0% | Execute Tests in Test | 2 days | Mon 12/12/05 | Tue 12/13/05 | 35 | Mary Phythian |
| 37 | 0% | Implementation Phase | 26 days | Thu 11/10/05 | Thu 12/15/05 | ||
| 38 | 0% | Prepare prod server for SAS applications | 1 day | Thu 11/10/05 | Thu 11/10/05 | Network Administrator[90%],Keith Andersen[10%] | |
| 39 | 0% | Obtain Approval | 1 day | Thu 12/15/05 | Thu 12/15/05 | ||
| 40 | 0% | Move Application to prod | 1 day | Thu 12/08/05 | Thu 12/08/05 | Network Administrator | |
| 41 | 0% | Perform Full System Run | 1 day | Fri 12/09/05 | Fri 12/09/05 | 40 | Mary Phythian |
| 42 | 0% | Execute Tests in Production | 1 day | Mon 12/12/05 | Mon 12/12/05 | 41 | Mary Phythian |
| 43 | 0% | Commercial Activities Inventory | 0.25 days | Fri 02/07/03 | Fri 02/07/03 | ||
| 44 | 0% | Requirements | 0.25 days | Fri 02/07/03 | Fri 02/07/03 | ||
| 45 | 0% | Analysis | 0.25 days | Fri 02/07/03 | Fri 02/07/03 | ||
| 46 | 0% | Development | 0.25 days | Fri 02/07/03 | Fri 02/07/03 | ||
| 47 | 0% | Test | 0.25 days | Fri 02/07/03 | Fri 02/07/03 | ||
| 48 | 0% | Implementation | 0.25 days | Fri 02/07/03 | Fri 02/07/03 | ||
| 49 | 1% | Projects on waiting list | 600 days | Mon 02/03/03 | Fri 05/20/05 | ||
| 50 | 0% | BA Direct (Benefits Administrators) | 30 days | Mon 02/03/03 | Fri 03/14/03 | ||
| 1 | 0% | BA-Direct | 30 days | Mon 02/03/03 | Fri 03/14/03 | ||
| 2 | 0% | BA-Direct | 30 days | Mon 02/03/03 | Fri 03/14/03 | ||
| 51 | 0% | Batch PMIS Loader(Hold) | 15 days | Tue 04/01/03 | Mon 04/21/03 | Bradley Paul | |
| 1 | 0% | Batch Loader - sets of PME480 and Transactions files available to Web-services | 15 days | Tue 04/01/03 | Mon 04/21/03 | ||
| 52 | 7% | P3/P3A Form Update (Hold) | 37.25 days | Mon 02/03/03 | Wed 03/26/03 | Bradley Paul | |
| 1 | 7% | P3 Form Update | 37.25 days | Mon 02/03/03 | Wed 03/26/03 | ||
| 2 | 56% | Loader Change | 1.25 days | Mon 02/03/03 | Tue 02/04/03 | ||
| 3 | 100% | Requirements | 0.25 days | Mon 02/03/03 | Mon 02/03/03 | ||
| 4 | 100% | Design | 0.25 days | Mon 02/03/03 | Mon 02/03/03 | 3 | |
| 5 | 80% | Code | 0.25 days | Mon 02/03/03 | Mon 02/03/03 | 4 | |
| 6 | 0% | Test | 0.25 days | Mon 02/03/03 | Mon 02/03/03 | 5 | |
| 7 | 0% | Implementation | 0.25 days | Tue 02/04/03 | Tue 02/04/03 | 6 | |
| 8 | 5% | Display Form Change | 36 days | Tue 02/04/03 | Wed 03/26/03 | 2 | |
| 9 | 25% | Requirements | 10 days | Tue 02/04/03 | Tue 02/18/03 | ||
| 10 | 0% | Code | 30 days | Tue 02/04/03 | Tue 03/18/03 | ||
| 11 | 0% | Test | 5 days | Tue 03/18/03 | Tue 03/25/03 | 10 | |
| 12 | 0% | Implementation | 1 day | Tue 03/25/03 | Wed 03/26/03 | 11 | |
| 53 | 0% | DHRM Intranet (Hold) | 15 days | Thu 05/01/03 | Wed 05/21/03 | Bradley Paul | |
| 1 | 0% | Intranet | 15 days | Thu 05/01/03 | Wed 05/21/03 | ||
| 54 | 0% | PMIS web interface (Hold) | 100 days | Mon 01/03/05 | Fri 05/20/05 | Bradley Paul | |
| 1 | 0% | Unisys Interface | 100 days | Mon 01/03/05 | Fri 05/20/05 | ||
| 2 | 0% | Design | 20 days | Mon 01/03/05 | Fri 01/28/05 | ||
| 3 | 0% | Development and Testing | 60 days | Mon 01/31/05 | Fri 04/22/05 | 2 | |
| 4 | 0% | Implementation and Evaluation | 20 days | Mon 04/25/05 | Fri 05/20/05 | 3 | |
| 55 | 0% | Security Form Web-Enable (Hold) | 26 days | Wed 09/01/04 | Wed 10/06/04 | Mary Phythian | |
| 1 | 0% | Automate Security Form | 26 days | Wed 09/01/04 | Wed 10/06/04 | ||
| 2 | 0% | System Design Phase | 11 days | Wed 09/01/04 | Wed 09/15/04 | ||
| 3 | 0% | Web Design | 5 days | Wed 09/01/04 | Tue 09/07/04 | Mary Phythian | |
| 4 | 0% | Database Design | 2 days | Wed 09/08/04 | Thu 09/09/04 | 3 | Mary Phythian |
| 5 | 0% | Define Processes(web) | 2 days | Fri 09/10/04 | Mon 09/13/04 | 4 | Mary Phythian |
| 6 | 0% | Define Security Specifications | 2 days | Tue 09/14/04 | Wed 09/15/04 | 5 | Mary Phythian |
| 7 | 0% | Development/Testing Phase | 15 days | Thu 09/16/04 | Wed 10/06/04 | 6 | |
| 8 | 0% | Create Database | 3 days | Thu 09/16/04 | Mon 09/20/04 | Mary Phythian | |
| 9 | 0% | Code Processes(web) | 12 days | Tue 09/21/04 | Wed 10/06/04 | 8 | Mary Phythian |
| 10 | 0% | Unit Test/Debug Processes on local machine | 2 days | Thu 09/16/04 | Fri 09/17/04 | Mary Phythian | |
| 11 | 0% | Move App and Db to devel server | 2 days | Mon 09/20/04 | Tue 09/21/04 | 10 | Mary Phythian[50%],Network Admin[50%] |
| 12 | 0% | Code Processes(wrapper) | 2 days | Wed 09/22/04 | Thu 09/23/04 | 11 | Mary Phythian |
| 13 | 0% | Unit Test/Debug Processes on devel (incudes wrapper testing) | 2 days | Fri 09/24/04 | Mon 09/27/04 | 12 | Mary Phythian |
| 14 | 0% | Implementation Phase | 3 days | Thu 09/16/04 | Mon 09/20/04 | 2 | |
| 15 | 0% | Complete Initial Project Production Release Form | 1 day | Thu 09/16/04 | Thu 09/16/04 | Mary Phythian | |
| 16 | 0% | Move App and DB to prod | 1 day | Fri 09/17/04 | Fri 09/17/04 | 15 | Network Admin |
| 17 | 0% | Execute Tests in Production | 1 day | Mon 09/20/04 | Mon 09/20/04 | 16 | Mary Phythian |
| 18 | 0% | Perform Full System Run | 1 day | Thu 09/16/04 | Thu 09/16/04 | Mary Phythian | |
| 56 | 0% | VIPERS Phase II | 15 days | Mon 02/03/03 | Fri 02/21/03 | ||
| 1 | 0% | VIPERS Phase II | 15 days | Mon 02/03/03 | Fri 02/21/03 | ||
| 2 | 0% | VIPERS Interface | 15 days | Mon 02/03/03 | Fri 02/21/03 | ||
| 57 | 0% | PMIS COBOL reports Migration from Mainframe (on Hold) | 74 days | Thu 07/01/04 | Tue 10/12/04 | ITECH Team | |
| 1 | 0% | Project Requirements | 15 days | Thu 07/01/04 | Wed 07/21/04 | ||
| 2 | 0% | Systems Analysis Phase | 32 days | Thu 07/01/04 | Fri 08/13/04 | ||
| 3 | 0% | Identify and Document Reports | 8 days | Thu 07/01/04 | Mon 07/12/04 | ||
| 4 | 0% | Survey existing COBOL reports and data inputs | 9 days | Tue 07/13/04 | Fri 07/23/04 | 3 | |
| 5 | 0% | Determine server side data repository needs | 2 days | Thu 07/01/04 | Fri 07/02/04 | ||
| 6 | 0% | Identify candidate reports to migrate | 3 days | Mon 07/26/04 | Wed 07/28/04 | 4 | |
| 7 | 0% | Develop conversion specifications for candidate reports | 15 days | Mon 07/26/04 | Fri 08/13/04 | 4 | |
| 8 | 0% | Identify report functional owners | 1 day | Tue 07/13/04 | Tue 07/13/04 | 3 | |
| 9 | 0% | Identify report recipients (report access security) | 2 days | Wed 07/14/04 | Thu 07/15/04 | 8 | |
| 10 | 0% | Get owner signoff to proceed for each report | 3 days | Fri 07/16/04 | Tue 07/20/04 | 9 | |
| 11 | 0% | Design Phase | 10 days | Mon 08/16/04 | Fri 08/27/04 | 2 | |
| 12 | 0% | Design report portal | 2 days | Mon 08/16/04 | Tue 08/17/04 | ||
| 13 | 0% | Design report prototypes | 4 days | Wed 08/18/04 | Mon 08/23/04 | 12 | |
| 14 | 0% | Design data repository | 2 days | Mon 08/16/04 | Tue 08/17/04 | ||
| 15 | 0% | Define Security Specifications | 1 day | Mon 08/16/04 | Mon 08/16/04 | ||
| 16 | 0% | Obtain functional owner sign offs | 4 days | Tue 08/24/04 | Fri 08/27/04 | 13 | |
| 17 | 0% | Development Phase | 20 days | Mon 08/30/04 | Fri 09/24/04 | 11 | |
| 18 | 0% | Develop data repository | 4 days | Mon 08/30/04 | Thu 09/02/04 | ||
| 19 | 0% | Develop legacy data feed to db | 4 days | Mon 08/30/04 | Mon 09/06/04 | ||
| 20 | 0% | Create web portal (page creation) | 10 days | Mon 08/30/04 | Fri 09/10/04 | ||
| 21 | 0% | Create web portal (application code) | 10 days | Mon 09/13/04 | Fri 09/24/04 | 20 | |
| 22 | 0% | Develop report prototypes (SAS) | 6 days | Mon 08/30/04 | Mon 09/06/04 | ||
| 23 | 0% | Obtain functional owner sign offs | 2 days | Mon 08/30/04 | Tue 08/31/04 | ||
| 24 | 0% | System Testing | 6 days | Mon 09/27/04 | Mon 10/04/04 | 17 | |
| 25 | 0% | Develop Test Scripts | 2 days | Mon 09/27/04 | Tue 09/28/04 | ||
| 26 | 0% | Execute Tests in Development | 2 days | Wed 09/29/04 | Thu 09/30/04 | 25 | |
| 27 | 0% | Validate new web reports against old COBOL reports | 2 days | Fri 10/01/04 | Mon 10/04/04 | 26 | |
| 28 | 0% | Obtain functional owner sign offs | 1 day | Mon 09/27/04 | Mon 09/27/04 | ||
| 29 | 0% | Implementation Phase | 6 days | Tue 10/05/04 | Tue 10/12/04 | 24 | |
| 30 | 0% | Establish production environment | 2 days | Tue 10/05/04 | Wed 10/06/04 | ||
| 31 | 0% | Phased migration of reports as completed | 2 days | Thu 10/07/04 | Fri 10/08/04 | 30 | |
| 32 | 0% | Execute Tests in Production | 2 days | Mon 10/11/04 | Tue 10/12/04 | 31 | |
| 33 | 0% | Add to ITECH webpage and security form | 1 day | Tue 10/05/04 | Tue 10/05/04 | ||
| 34 | 0% | Training | 1 day | Tue 10/05/04 | Tue 10/05/04 | ||
| 11 | 22% | LEGACY PROJECTS | 632 days | Mon 03/03/03 | Tue 08/02/05 | ||
| 1 | 22% | Special Projects | 632 days | Mon 03/03/03 | Tue 08/02/05 | ||
| 2 | 0% | EEO-4 Bi-Annual Process-Automate | 20.7 days | Fri 01/21/05 | Fri 02/18/05 | Norm Christensen | |
| 1 | 0% | EEO-4 Unisys Legacy Process | 20.7 days | Fri 01/21/05 | Fri 02/18/05 | Norm Christensen | |
| 2 | 0% | Convert & Migrate COBOL Batch Process to Production Stds | 17 days | Fri 01/21/05 | Mon 02/14/05 | ||
| 3 | 0% | Analyze and Remediate Programs as Needed | 15 days | Fri 01/21/05 | Thu 02/10/05 | Norm Christensen | |
| 4 | 0% | Build FTP of Existing Fed Output Files | 1 day | Fri 02/11/05 | Fri 02/11/05 | 3 | Norm Christensen |
| 5 | 0% | Schedule Batch Jobs as DIT-SAMS "On Request" | 2 days | Fri 02/11/05 | Mon 02/14/05 | 3 | Norm Christensen |
| 6 | 0% | Build Data Feed for WEB Reporting Tool | 6 days | Fri 01/21/05 | Fri 01/28/05 | Norm Christensen | |
| 7 | 0% | Document Unisys EEO-4 Process | 3 days | Tue 02/15/05 | Fri 02/18/05 | 2 | Norm Christensen |
| 3 | 3% | EPR - Legacy Changes | 632 days | Mon 03/03/03 | Tue 08/02/05 | ||
| 1 | 0% | Report Development - EPR Annual FTE Report for Governor & General Assembly | 372 days | Mon 03/03/03 | Tue 08/03/04 | Nancy Balderson,Keith Andersen | |
| 2 | 0% | Develop Specifications | 2 days | Mon 08/02/04 | Tue 08/03/04 | Nancy Balderson | |
| 3 | 0% | Develop Program / Unit Test | 4 days | Mon 03/03/03 | Thu 03/06/03 | Keith Andersen,Balderson | |
| 4 | 0% | Implement in Production | 1 day | Mon 03/03/03 | Mon 03/03/03 | Keith Andersen | |
| 5 | 0% | EPR Modification - Quasi-Full-time Employees (waiting on business requirements) | 20 days | Mon 03/03/03 | Fri 03/28/03 | Nancy Balderson,Norman Christensen | |
| 6 | 0% | Requirements Definition | 5 days | Mon 03/03/03 | Fri 03/07/03 | ||
| 7 | 0% | Define and Document Requirements | 1 day | Mon 03/03/03 | Mon 03/03/03 | Balderson,Weaver | |
| 8 | 0% | Obtain Approval - AHRS | 4 days | Tue 03/04/03 | Fri 03/07/03 | 7 | Weaver |
| 9 | 0% | Analsyis & Design | 3 days | Mon 03/10/03 | Wed 03/12/03 | 6 | |
| 10 | 0% | Perform Analysis | 1 day | Mon 03/10/03 | Mon 03/10/03 | Balderson | |
| 11 | 0% | Develop Specs | 1 day | Tue 03/11/03 | Tue 03/11/03 | 10 | Balderson |
| 12 | 0% | Obtain Approval - AHRS | 1 day | Wed 03/12/03 | Wed 03/12/03 | 11 | Weaver |
| 13 | 0% | Development | 11 days | Thu 03/13/03 | Thu 03/27/03 | 9 | |
| 14 | 0% | Prepare Test Environment & Data | 3 days | Thu 03/13/03 | Mon 03/17/03 | Christensen | |
| 15 | 0% | Modify Program - EPR510 | 3 days | Tue 03/18/03 | Thu 03/20/03 | 14 | Christensen |
| 16 | 0% | Test Program | 3 days | Fri 03/21/03 | Tue 03/25/03 | 15 | Christensen |
| 17 | 0% | Obtain Approval - AHRS | 2 days | Wed 03/26/03 | Thu 03/27/03 | 16 | Weaver |
| 18 | 0% | Implementation | 1 day | Fri 03/28/03 | Fri 03/28/03 | 13 | |
| 19 | 0% | Move Programs to Production | 1 day | Fri 03/28/03 | Fri 03/28/03 | Christensen | |
| 20 | 3% | DRS "Floating Mel" Positions & Breakout of Faculty Salaried Positions & Adjunct Faculty | 236 days | Tue 09/07/04 | Tue 08/02/05 | Nancy Balderson,Norman Christensen,David Savanyu | |
| 21 | 53% | Requirements Phase | 15 days | Tue 09/07/04 | Mon 09/27/04 | ||
| 22 | 80% | Identify and Document Requirements | 10 days | Tue 09/07/04 | Mon 09/20/04 | Balderson,Christensen,Weaver | |
| 23 | 0% | Obtain Approval - AHRS | 5 days | Tue 09/21/04 | Mon 09/27/04 | 22 | Weaver |
| 24 | 0% | Systems Analysis Phase | 46 days | Tue 09/28/04 | Tue 11/30/04 | 21 | |
| 25 | 0% | Review Application Code | 20 days | Tue 09/28/04 | Tue 10/26/04 | Balderson,Christensen | |
| 26 | 0% | Map EPR Data Fields | 20 days | Wed 10/27/04 | Tue 11/23/04 | 25 | Christensen |
| 27 | 0% | Validate / Update PMIS Role Codes Required for Faculty Breakout | 3 days | Wed 11/24/04 | Fri 11/26/04 | 26 | Balderson |
| 28 | 0% | Obtain Approval - AHRS | 2 days | Mon 11/29/04 | Tue 11/30/04 | 27 | Weaver |
| 29 | 0% | Design Phase | 40 days | Wed 12/01/04 | Tue 01/25/05 | 24 | |
| 30 | 0% | Develop Specs - EPR On-Line Programs / Screen Modifications | 20 days | Wed 12/01/04 | Tue 12/28/04 | Balderson,Christensen | |
| 31 | 0% | Develop Specs - EPR Database Extract/Load & Other Support Pgms | 15 days | Wed 12/01/04 | Tue 12/21/04 | 24 | Christensen |
| 32 | 0% | Develop Specs - EPR Batch Programs | 20 days | Wed 12/22/04 | Tue 01/18/05 | 31 | Balderson,Christensen |
| 33 | 0% | Develop Specs - Mel Breakout by New Faculty Categories | 3 days | Wed 01/19/05 | Fri 01/21/05 | 32 | Christensen |
| 34 | 0% | Obtain Approval - AHRM | 2 days | Mon 01/24/05 | Tue 01/25/05 | 33 | Weaver |
| 35 | 0% | Development Phase | 71 days | Wed 01/26/05 | Wed 05/04/05 | 29 | |
| 36 | 0% | Database Changes - Development / Modification | 5 days | Wed 01/26/05 | Tue 02/01/05 | Savanyu | |
| 37 | 0% | Resize State Total Area, As Needed | 1 day | Wed 02/02/05 | Wed 02/02/05 | 36 | Savanyu |
| 38 | 0% | DPS Screen Changes - Development / Modification | 10 days | Thu 02/03/05 | Wed 02/16/05 | 37 | Savanyu |
| 39 | 0% | Modify / Unit Test EPR Database Extract/Load and Other Support Programs | 12 days | Thu 02/17/05 | Fri 03/04/05 | 38 | Christensen |
| 40 | 0% | Establish Test Environment | 5 days | Mon 03/07/05 | Fri 03/11/05 | 39 | Christensen |
| 41 | 0% | Modify / Unit Test - Programs to Store MEL for New Faculty Categories | 8 days | Mon 03/14/05 | Wed 03/23/05 | 40 | Christensen |
| 42 | 0% | Modify / Unit Test EPR Batch Programs | 30 days | Thu 03/24/05 | Wed 05/04/05 | 41 | Christensen,Balderson |
| 43 | 0% | Modify / Unit Test EPR On-Line Programs | 15 days | Thu 02/03/05 | Wed 02/23/05 | 37 | Savanyu |
| 44 | 0% | System Testing | 20 days | Thu 05/05/05 | Wed 06/01/05 | 35 | |
| 45 | 0% | Develop Test Plan / Scripts | 5 days | Thu 05/05/05 | Wed 05/11/05 | Christensen,Balderson | |
| 46 | 0% | Execute Test Plan / Scripts | 10 days | Thu 05/12/05 | Wed 05/25/05 | 45 | Balderson,Christensen |
| 47 | 0% | Perform System Batch Cycle | 3 days | Thu 05/26/05 | Mon 05/30/05 | 46 | Christensen,Balderson |
| 48 | 0% | Produce / Update System Documentation | 15 days | Thu 05/05/05 | Wed 05/25/05 | 35 | Christensen |
| 49 | 0% | Obtain Approval - AHRS | 5 days | Thu 05/26/05 | Wed 06/01/05 | 48 | Weaver |
| 50 | 0% | Implementation Phase | 2 days | Mon 08/01/05 | Tue 08/02/05 | 44 | |
| 51 | 0% | Re-Establish Production Environment (Database, Programs, Screens) | 2 days | Mon 08/01/05 | Tue 08/02/05 | Christensen,Savanyu | |
| 52 | 5% | EPR Modification - Addition of New Funding Data Occurrences | 18.5 days | Mon 03/01/04 | Thu 03/25/04 | Nancy Balderson,Norman Christensen | |
| 53 | 18% | Requirements Definition | 5 days | Mon 03/01/04 | Fri 03/05/04 | ||
| 54 | 90% | Define and Document Requirements | 1 day | Mon 03/01/04 | Mon 03/01/04 | Balderson,Weaver | |
| 55 | 0% | Obtain Approval - AHRS | 4 days | Tue 03/02/04 | Fri 03/05/04 | 54 | Weaver |
| 56 | 0% | Analsyis & Design | 3 days | Mon 03/08/04 | Wed 03/10/04 | 53 | |
| 57 | 0% | Perform Analysis | 1 day | Mon 03/08/04 | Mon 03/08/04 | Balderson | |
| 58 | 0% | Develop Specs | 1 day | Tue 03/09/04 | Tue 03/09/04 | 57 | Balderson |
| 59 | 0% | Obtain Approval - AHRS | 1 day | Wed 03/10/04 | Wed 03/10/04 | 58 | Weaver |
| 60 | 0% | Development | 9.5 days | Thu 03/11/04 | Wed 03/24/04 | 56 | |
| 61 | 0% | Prepare Test Environment & Data | 3 days | Thu 03/11/04 | Mon 03/15/04 | Balderson | |
| 62 | 0% | Modify Program - EPR510 | 3 days | Tue 03/16/04 | Thu 03/18/04 | 61 | Balderson |
| 63 | 0% | Test Program | 1.5 days | Fri 03/19/04 | Mon 03/22/04 | 62 | Christensen,Balderson |
| 64 | 0% | Obtain Approval - AHRS | 2 days | Mon 03/22/04 | Wed 03/24/04 | 63 | Weaver |
| 65 | 0% | Implementation | 1 day | Wed 03/24/04 | Thu 03/25/04 | 60 | |
| 66 | 0% | Move Programs to Production | 1 day | Wed 03/24/04 | Thu 03/25/04 | Christensen | |
| 4 | 76% | Written Notices (PMIS Development) | 131 days | Mon 02/02/04 | Mon 08/02/04 | ||
| 1 | 76% | Production of Written Notices in PMIS | 131 days | Mon 02/02/04 | Mon 08/02/04 | Nancy Balderson,David Savanyu | |
| 2 | 100% | Requirements Definition | 23 days | Mon 02/02/04 | Wed 03/03/04 | ||
| 3 | 100% | Identify and Document Requirements | 20 days | Mon 02/02/04 | Fri 02/27/04 | Balderson | |
| 4 | 100% | Obtain Approval of Requirements | 3 days | Mon 03/01/04 | Wed 03/03/04 | 3 | Balderson,Weaver |
| 5 | 100% | System Analysis & Design (General / Detail) | 27 days | Thu 03/04/04 | Fri 04/09/04 | 2 | |
| 6 | 100% | Perform Analysis | 5 days | Thu 03/04/04 | Wed 03/10/04 | Savanyu,Balderson | |
| 7 | 100% | Determine Output Record Designs | 5 days | Thu 03/11/04 | Wed 03/17/04 | 6 | Balderson |
| 8 | 100% | Determine Input / Output Interface (Screen) Designs | 5 days | Thu 03/18/04 | Wed 03/24/04 | 7 | Savanyu |
| 9 | 100% | Develop Specifications for Development / Modification of Programs | 10 days | Thu 03/25/04 | Wed 04/07/04 | 8 | Balderson |
| 10 | 100% | Obtain Aproval from AHRS | 2 days | Thu 04/08/04 | Fri 04/09/04 | 9 | Balderson,Weaver |
| 11 | 86% | Develop Dcoumentation for PMIS User Group | 22 days | Mon 04/05/04 | Tue 05/04/04 | ||
| 12 | 100% | Produce Document | 12 days | Mon 04/05/04 | Tue 04/20/04 | ||
| 13 | 0% | Modified Specs based on Recommendations from PMIS User Group | 2 days | Mon 05/03/04 | Tue 05/04/04 | ||
| 14 | 39% | Development | 80 days | Mon 04/12/04 | Fri 07/30/04 | 5 | |
| 15 | 0% | Develop Test ECL Runstreams | 1 day | Mon 04/12/04 | Mon 04/12/04 | Savanyu | |
| 16 | 80% | Develop or Modify Programs / Unit Test | 15 days | Mon 06/14/04 | Fri 07/02/04 | Savanyu | |
| 17 | 0% | Modify Programs based on Recommendations from PMIS Users Group | 5 days | Mon 07/12/04 | Fri 07/16/04 | Savanyu | |
| 18 | 0% | Perform Testing | 5 days | Mon 07/19/04 | Fri 07/23/04 | 17 | Team |
| 19 | 0% | Correct Problems / Perform Final Testing | 5 days | Mon 07/26/04 | Fri 07/30/04 | 18 | Savanyu,Team |
| 20 | 0% | Implementation | 1 day | Mon 08/02/04 | Mon 08/02/04 | 14 | |
| 21 | 0% | Move Programs to Production | 1 day | Mon 08/02/04 | Mon 08/02/04 | Savanyu | |
| 22 | 0% | Develop Production ECL Runstreams | 1 day | Mon 08/02/04 | Mon 08/02/04 | Savanyu | |
| 5 | 50% | Descontinuity of IBM-3270 Emulator Access to UNISYS | 191 days | Mon 05/10/04 | Mon 01/31/05 | ||
| 1 | 50% | Unisys 3270 Access | 191 days | Mon 05/10/04 | Mon 01/31/05 | Norman Christensen | |
| 2 | 50% | Coordinate with VITA to Identify/Test Candidate Solutions | 191 days | Mon 05/10/04 | Mon 01/31/05 | Norman Christensen | |
| 3 | 50% | Coordinate with VITA to Support Solution Implementation | 175 days | Tue 06/01/04 | Mon 01/31/05 | Norman Christensen | |
| 6 | 12% | Projects on Waiting List | 24 days | Mon 01/05/04 | Thu 02/05/04 | ||
| 7 | 12% | PMIS/Non-PMIS Data Consolidation (On Hold) | 24 days | Mon 01/05/04 | Thu 02/05/04 | ||
| 1 | 12% | Improve Merge of PMIS NON-PMIS Data Feed to SAS (On Hold) | 24 days | Mon 01/05/04 | Thu 02/05/04 | Nancy Balderson | |
| 2 | 95% | Analysis | 2 days | Mon 01/05/04 | Tue 01/06/04 | ||
| 3 | 95% | Analysis: Evaluate Existing Feed Problem | 2 days | Mon 01/05/04 | Tue 01/06/04 | Norm Christensen,Nancy Balderson[50%] | |
| 4 | 11% | Design: Develop Alternatives to Improve Data Feed | 8 days | Wed 01/07/04 | Fri 01/16/04 | 2 | |
| 5 | 90% | Define PME480 New "Data-Type" Values | 1 day | Wed 01/07/04 | Wed 01/07/04 | Nancy Balderson[25%],Norm Christensen[75%] | |
| 6 | 0% | Develop Edit Process to Scrub NON-PMIS Salary Data | 7 days | Thu 01/08/04 | Fri 01/16/04 | 5 | Nancy Balderson[25%],Norm Christensen[75%] |
| 7 | 0% | Development: Code & Test Proposed Changes | 12 days | Mon 01/19/04 | Tue 02/03/04 | 6 | Nancy Balderson[25%],Norm Christensen[75%] |
| 8 | 0% | Implement: Migrate Changes to Production | 2 days | Wed 02/04/04 | Thu 02/05/04 | 7 | Norm Christensen |
| 12 | 43% | OFFICE OF HEALTH BENEFITS PROJECTS | 135 days | Mon 03/08/04 | Fri 09/10/04 | ||
| 1 | 43% | BES - Legacy - On-line/Batch | 135 days | Mon 03/08/04 | Fri 09/10/04 | ||
| 2 | 0% | BES Turn-around Documents (on hold due to other priorities) | 52 days | Thu 07/01/04 | Fri 09/10/04 | ||
| 3 | 0% | Requirements | 15 days | Thu 07/01/04 | Wed 07/21/04 | Brenda Kirby | |
| 4 | 0% | Analysis | 10 days | Thu 07/22/04 | Wed 08/04/04 | 3 | Dan Farrell |
| 5 | 0% | Programming | 20 days | Thu 08/05/04 | Wed 09/01/04 | 4 | |
| 6 | 0% | Testing | 5 days | Thu 09/02/04 | Wed 09/08/04 | 5 | Dan Farrell |
| 7 | 0% | Implementation | 2 days | Thu 09/09/04 | Fri 09/10/04 | 6 | Dan Farrell |
| 8 | 40% | Convert BES extract | 80 days | Mon 03/08/04 | Fri 06/25/04 | Dan Farrell | |
| 9 | 100% | Requirements | 15 days | Mon 03/08/04 | Fri 03/26/04 | Dan Farrell | |
| 10 | 100% | Analysis | 15 days | Mon 04/05/04 | Fri 04/23/04 | 9 | Dan Farrell |
| 11 | 0% | Programming | 30 days | Mon 04/26/04 | Fri 06/04/04 | 10 | Dan Farrell |
| 12 | 0% | Testing | 10 days | Mon 06/07/04 | Fri 06/18/04 | 11 | Dan Farrell |
| 13 | 0% | Implementation | 5 days | Mon 06/21/04 | Fri 06/25/04 | 12 | Dan Farrell |
| 14 | 100% | Convert SSN as Primary Key to Alternate-Id | 77 days | Mon 05/17/04 | Tue 08/31/04 | David Savanyu | |
| 15 | 100% | Requirements | 5 days | Mon 05/17/04 | Fri 05/21/04 | David Savanyu | |
| 16 | 100% | Analysis | 10 days | Mon 05/31/04 | Fri 06/11/04 | 15 | David Savanyu |
| 17 | 100% | Programming | 20 days | Mon 07/26/04 | Fri 08/20/04 | 16 | David Savanyu |
| 18 | 100% | Testing | 5 days | Mon 08/23/04 | Fri 08/27/04 | 17 | David Savanyu |
| 19 | 100% | Implementation | 2 days | Mon 08/30/04 | Tue 08/31/04 | 18 | David Savanyu |
| 13 | 44% | PRODUCTION MAINTENANCE | 380 days | Mon 04/05/04 | Fri 09/16/05 | ||
| 1 | 43% | BES Systems Maintenance | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 2 | 50% | BES On-Line Legacy System | 261 days | Thu 07/01/04 | Thu 06/30/05 | David Savanyu | |
| 3 | 50% | Monitor Production Processes | 253.5 days | Thu 07/01/04 | Thu 06/30/05 | David Savanyu | |
| 4 | 50% | Resolve Production Problems | 261 days | Thu 07/01/04 | Thu 06/30/05 | David Savanyu | |
| 5 | 50% | Ad Hoc Requests | 261 days | Thu 07/01/04 | Thu 06/30/05 | David Savanyu | |
| 6 | 50% | BES Batch Legacy System | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 7 | 50% | Run BES Production | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 8 | 50% | Monitor Production Processes | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 9 | 50% | Resolve Production Problems | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 10 | 50% | Ad Hoc Requests | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 11 | 50% | BES Other Routine Systems - Ongoing | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 12 | 50% | Administrative Tasks | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 13 | 50% | Technical Tasks - Systems Maintenance | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 14 | 50% | Ad Hoc Requests | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 15 | 10% | Revamp Daily BES Batch Runs | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 16 | 10% | VRS Bill Premium Reconciliation - Ongoing | 261 days | Thu 07/01/04 | Thu 06/30/05 | Dan Farrell | |
| 17 | 48% | PMIS Systems Maintenance | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 18 | 50% | PMIS On-Line Legacy System | 261 days | Thu 07/01/04 | Thu 06/30/05 | David Savanyu | |
| 19 | 50% | Monitor Production Processes | 253.5 days | Thu 07/01/04 | Thu 06/30/05 | David Savanyu | |
| 20 | 50% | Resolve Production Problems | 261 days | Thu 07/01/04 | Thu 06/30/05 | David Savanyu | |
| 21 | 50% | Ad Hoc Requests | 261 days | Thu 07/01/04 | Thu 06/30/05 | David Savanyu | |
| 22 | 50% | PMIS Batch Legacy System | 261 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey | |
| 23 | 50% | Run PMIS Production | 253.5 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey | |
| 24 | 50% | Monitor Production Processes | 253.5 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey | |
| 25 | 50% | Resolve Production Problems | 261 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey | |
| 26 | 50% | Ad Hoc Requests | 261 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey | |
| 27 | 50% | PMIS Other Routine Systems | 261 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey,David Savanyu | |
| 28 | 50% | Administrative Tasks | 260 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey,David Savanyu | |
| 29 | 50% | Technical Tasks - Systems Maintenance | 247 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey,David Savanyu | |
| 30 | 50% | Transaction Retractions (On Going) | 261 days | Thu 07/01/04 | Thu 06/30/05 | Balderson | |
| 31 | 50% | Analysis of PMIS Transactions | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 32 | 50% | Retract PMIS Transactions | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 33 | 0% | Faculty Salary Average | 151 days | Mon 07/05/04 | Mon 01/31/05 | Norman Christensen | |
| 1 | 0% | Faculty Salary Average Process | 151 days | Mon 07/05/04 | Mon 01/31/05 | ||
| 2 | 0% | Expected Baseline Run: July-August 2004? | 42 days | Mon 07/05/04 | Tue 08/31/04 | Norman Christensen | |
| 3 | 0% | Run "Production" Process: January 2005 | 20 days | Tue 01/04/05 | Mon 01/31/05 | Norman Christensen | |
| 34 | 0% | EEO4 Batch Legacy System | 380 days | Mon 04/05/04 | Fri 09/16/05 | Norman Christensen | |
| 1 | 0% | Run biennial EEO4 Production | 30 days | Mon 08/08/05 | Fri 09/16/05 | Norman Christensen | |
| 2 | 0% | Monitor/Maintain Production Processes | 5 days | Mon 04/05/04 | Fri 04/09/04 | Norman Christensen | |
| 3 | 0% | Ad Hoc Requests | 5 days | Mon 04/05/04 | Fri 04/09/04 | Norman Christensen | |
| 35 | 5% | EPR Batch Legacy System | 88 days | Tue 06/01/04 | Thu 09/30/04 | Norman Christensen | |
| 1 | 5% | Run Add/Remove Agency Process | 48 days | Tue 06/01/04 | Thu 08/05/04 | Norman Christensen | |
| 2 | 5% | Run Load New FY MELs Process | 71 days | Tue 06/01/04 | Tue 09/07/04 | Norman Christensen | |
| 3 | 5% | Document System Processes | 88 days | Tue 06/01/04 | Thu 09/30/04 | Norman Christensen | |
| 36 | 50% | P3/P3A Legacy / Client-Server Online System | 261 days | Thu 07/01/04 | Thu 06/30/05 | Bradley Paul,Steve Hastey | |
| 37 | 50% | Monitor P3/P3A Activity - Ongoing | 206.25 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey,Bradley Pau | |
| 38 | 50% | Resolve Production Problems | 261 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey,Bradley Paul | |
| 39 | 50% | EmployeeDirect - Systems Maintenance Support | 261 days | Thu 07/01/04 | Thu 06/30/05 | Bradley Paul | |
| 40 | 50% | Monitor Production Processes - Ongoing | 261 days | Thu 07/01/04 | Thu 06/30/05 | Bradley Paul | |
| 41 | 50% | Resolve Production Problems - Ongoing | 261 days | Thu 07/01/04 | Thu 06/30/05 | Bradley Paul | |
| 42 | 50% | Non-PMIS Data Collection (Ongoing) | 261 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey | |
| 43 | 50% | Collect data from additional agencies as required | 224.5 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey | |
| 44 | 50% | Applicant Flow - Maintenance (on Going) | 261 days | Thu 07/01/04 | Thu 06/30/05 | Balderson | |
| 45 | 50% | Perform Validation, Analysis, and Correction of Incoming Applicant Data | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 46 | 50% | Web Tools Maintenance | 261 days | Thu 07/01/04 | Thu 06/30/05 | Balderson | |
| 47 | 50% | e480 Tool | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 48 | 50% | eTrans Tool | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 49 | 50% | EEO Assessment tools | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 50 | 50% | Transaction Log File and SAS Reporting Files | 261 days | Thu 07/01/04 | Thu 06/30/05 | Balderson | |
| 14 | 47% | SYSTEMS SUPPORT AND SUPPORT TO USERS | 472 days | Wed 09/10/03 | Thu 06/30/05 | ||
| 15 | 46% | EXTERNAL Support | 472 days | Wed 09/10/03 | Thu 06/30/05 | ||
| 16 | 53% | Application Support to Agencies | 472 days | Wed 09/10/03 | Thu 06/30/05 | ||
| 1 | 54% | BERT Application Support to VITA | 472 days | Wed 09/10/03 | Thu 06/30/05 | Norman Christensen | |
| 2 | 100% | Repair System so VITA Can Run Budget | 124 days | Wed 09/10/03 | Mon 03/01/04 | Norman Christensen | |
| 3 | 100% | Document System Processes | 49 days | Mon 03/22/04 | Thu 05/27/04 | Norman Christensen | |
| 4 | 100% | Support Re-engineering of System | 66 days | Mon 12/01/03 | Mon 03/01/04 | Norman Christensen | |
| 5 | 60% | FY 04/05 Fiscal Year Rollover | 186 days | Tue 03/16/04 | Tue 11/30/04 | Norman Christensen | |
| 6 | 40% | Routine System Support: Maintain Production & Ad Hoc Reporting | 349 days | Mon 03/01/04 | Thu 06/30/05 | Norman Christensen | |
| 7 | 35% | Support VITA PERSONNEL Application | 361 days | Thu 02/12/04 | Thu 06/30/05 | ||
| 8 | 50% | Other Application Support | 261 days | Thu 07/01/04 | Thu 06/30/05 | Steve Hastey | |
| 9 | 50% | Ad-Hoc requests | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 10 | 50% | Support to agencies in-house data systems | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 17 | 44% | Other External Support | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 18 | 20% | PMIS HelpDesk | 261 days | Thu 07/01/04 | Thu 06/30/05 | JoAnn Stamper,Lona Pugh | |
| 19 | 50% | PMIS Training Materials updates (Quarterly) | 200 days | Mon 07/05/04 | Fri 04/08/05 | JoAnn Stamper | |
| 20 | 100% | First Quarter | 5 days | Mon 07/05/04 | Fri 07/09/04 | ||
| 21 | 100% | Second Quarter | 5 days | Mon 10/04/04 | Fri 10/08/04 | ||
| 22 | 0% | Third Quarter | 5 days | Mon 01/03/05 | Fri 01/07/05 | ||
| 23 | 0% | Fourth Quarter | 5 days | Mon 04/04/05 | Fri 04/08/05 | ||
| 24 | 50% | PMIS Data Entry Training - (Quarterly) | 192 days | Mon 07/12/04 | Tue 04/05/05 | JoAnn Stamper | |
| 25 | 100% | First Quarter | 2 days | Mon 07/12/04 | Tue 07/13/04 | ||
| 26 | 100% | Second Quarter | 2 days | Mon 10/11/04 | Tue 10/12/04 | ||
| 27 | 0% | Third Quarter | 2 days | Mon 01/10/05 | Tue 01/11/05 | ||
| 28 | 0% | Fourth Quarter | 2 days | Mon 04/04/05 | Tue 04/05/05 | ||
| 29 | 50% | EPR agency data collection | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 30 | 50% | BES HelpDesk | 261 days | Thu 07/01/04 | Thu 06/30/05 | JoAnn Stamper,Lona Pugh | |
| 31 | 50% | BES Training Materials updates (Quarterly) | 200 days | Mon 07/05/04 | Fri 04/08/05 | JoAnn Stamper | |
| 32 | 100% | First Quarter | 5 days | Mon 07/05/04 | Fri 07/09/04 | ||
| 33 | 100% | Second Quarter | 5 days | Mon 10/04/04 | Fri 10/08/04 | ||
| 34 | 0% | Third Quarter | 5 days | Mon 01/03/05 | Fri 01/07/05 | ||
| 35 | 0% | Fourth Quarter | 5 days | Mon 04/04/05 | Fri 04/08/05 | ||
| 36 | 50% | BES Data Entry Training - (Quarterly) | 191 days | Mon 07/12/04 | Mon 04/04/05 | JoAnn Stamper | |
| 37 | 100% | First Quarter | 1 day | Mon 07/12/04 | Mon 07/12/04 | ||
| 38 | 100% | Second Quarter | 1 day | Mon 10/11/04 | Mon 10/11/04 | ||
| 39 | 0% | Third Quarter | 1 day | Mon 01/10/05 | Mon 01/10/05 | ||
| 40 | 0% | Fourth Quarter | 1 day | Mon 04/04/05 | Mon 04/04/05 | ||
| 41 | 50% | Listserver Support | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 42 | 50% | Maintenance of Email Lists | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 43 | 50% | Leadership Communiqué support | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 44 | 47% | INTERNAL Support | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 45 | 0% | Data Security Access Administration | 261 days | Thu 07/01/04 | Thu 06/30/05 | JoAnn Stamper,Timothy Connor | |
| 46 | 50% | Network Support | 261 days | Thu 07/01/04 | Thu 06/30/05 | Timothy Connor | |
| 47 | 50% | Desktop / Laptop | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 48 | 50% | Other peripherals support | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 49 | 50% | Network Administration | 261 days | Thu 07/01/04 | Thu 06/30/05 | Allen Kass | |
| 50 | 50% | Servers | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 51 | 50% | Backup Exchange & File Server | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 52 | 50% | Archive Agency Folders | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 53 | 50% | Monitor Systems for normal operation | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 54 | 50% | Listserver Additions & Changes | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 55 | 50% | Ad-Hoc Requests | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 56 | 50% | Administrative tasks | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 57 | 50% | Systems Administration | 261 days | Thu 07/01/04 | Thu 06/30/05 | Bradley Paul | |
| 58 | 50% | SQL server | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 59 | 50% | IIS server | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 60 | 50% | Scheduler | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 61 | 50% | MITEM | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 62 | 50% | Oracle | 261 days | Thu 07/01/04 | Thu 06/30/05 | ||
| 63 | 50% | UNIX | 261 days | Thu 07/01/04 | Thu 06/30/05 |